Cost risk adjustment (step 2)
Contents: This section of the SSRO's guidance describes the cost risk adjustment, step 2 of the contract profit rate.
3.1 | Section 17(2) of the Act, and regulation 11(3), set out the requirement for the cost risk adjustment:
|
3.2 | Section 30 of the Act sets out that “[the Act] and single source contract regulations apply to qualifying subcontracts (and to sub-contractors) as they apply to qualifying defence contracts (and to primary contractors)”. In the case of a qualifying sub-contract, the calculation of the cost risk adjustment is agreed between the sub-contractor and the contracting authority, rather than the Secretary of State, and this guidance must be modified by reading references to the Secretary of State as the contracting authority and references to the contractor as the sub-contractor. |
3.5 | Regulation 10(2) states that the parties to a qualifying defence contract may agree which regulated pricing method is to be used for that contract. The parties can also agree a different pricing method for defined components of the contract (regulation 10(3)). |
3.6 | There are six regulated pricing methods that the parties to a qualifying defence contract may decide to use, as set out in regulation 10(4) to 10(11). All regulated pricing methods use either an estimate or actual Allowable Cost base. |
3.8 | The purpose of the cost risk adjustment is to incorporate into the contract profit rate an addition or deduction to reflect the risk that the contractor’s actual Allowable Costs in delivering the requirement will differ from the estimated Allowable Costs included in the contract price. While one factor will be the proportion of actual versus estimated costs included in the pricing method, other factors also drive risk. The adjustment should be agreed by considering the principles stated at paragraph 3.17. |
3.9 | For qualifying defence contracts that are based on the cost-plus or estimate-based fee regulated pricing methods (refer to regulation 10), the cost risk adjustment should be minus 25 per cent, because actual Allowable Costs are used to determine the costs to be paid, although the Secretary of State and the contractor should always have regard to the principles at paragraph 3.17. |
3.10 | For all other regulated pricing methods, the adjustment may vary from minus 25 per cent to plus 25 per cent, depending on the risk of actual Allowable Costs differing from estimated Allowable Costs, using the following guidance and the principles stated at paragraph 3.17. |
3.14 | The SSRO recognises that for some defence contracts most of the cost risk associated with one or more sub-contracts is held by, or assigned to, the Secretary of State. It is appropriate to recognise these circumstances when agreeing a cost risk adjustment. The cost risk adjustment should reflect the reduced risk of the primary contractor’s actual Allowable Costs under the contract differing from its estimated Allowable Costs, thus recognising the reduced risk held by the prime contractor associated with the sub-contract(s). |
3.17 | The contractor and the Secretary of State must have regard to the following principles (which are not exhaustive) when determining the cost risk adjustment. The adjustment should:
|
SSRO Determination: In 2016 the SSRO issued a determination on the appropriate cost risk adjustment. Link to full referral |